20.07.2021

Putting S61 Express road in the section Stawiski – Szczuczyn into operation

Tags:

On 20th July, 2021 GDDKiA released for the drivers another section of dual carriageway S61 expressway, from Stawiski interchange (not including the interchange) to the beginning of Szczuczyn bypass, the construction of which was under the supervision of TPF Sp. z o.o company.

The contract on the construction works with Budimex company was signed in November 31, 2017. After the design works and recievement of the decision on project implementation in September 31, 2019, the contractor started the works in the area.

After two years of the construction works in August 20, 2021, another S61 section was released for the drivers. In September 20, 2021 the above section applies constant traffic organization, thanks to which the drivers are able to use freely all the parameters of the expressway.

The carriageways of the section have a concrete paving and two 3,5 m long lanes (plus 2,5 m long emergency runway). They are adjusted to the heaviest traffic (KR7 category) with a capacity of 11,5 tones per axle.

In Stawiski - Szczuczyn section of S61 road there are two rest areas constructed: MOP Zabiele Zachód iand MOP Zabiele Wschód.

Find out more about the project HERE.