The upgrading of the lock and control room at Januszkowice barrage

TPF Sp. z o.o. implements for State Water Holding Polish Waters (Wody Polskie) the following service: Project Engineer Investor's Supervision over the following project implementation: Upgrading of the lock and control room at Januszkowice barrage, along with the outport reconstruction.

Within the scope of upgrading of the lock and control room at Krapkowice barrage, along with the outport reconstruction it is planned:

Task 1 - To reconstruct the existing watertight lock along with the reconstruction of the existing small lock by its partial demolition and construction of a 190m long lock instead of it.

Task 1 B - - To construct a technological footbridge in the section from the left bridgehead of the weir to the left coast of Oder river canal over the lock chambers.

Task 1 A - To regulate the right coast of Oder river below the weir and MEW exit at Januszkowice barrage, along with coast verge implementation and reconstruction of a dam separating from lower water.

Investor: State Water Holding "Polish Waters" (Wody Polskie)
Location: Opole Voivodeship, Poland
Service value: PLN 3,1 mln gross
Implementation period: 03.2021 – today

Cooperating with: