The project includes three separate ventures consisting of the following works:
- Krępa weir in 114+500 km of Oder river,
- Jaz Groszowice w km 144+750 rzeki Odry, w mieście Opole,
- Dobrzeń weir in 164,200 km of Oder river,
The project includes three separate ventures consisting of the following works:
- replacement of sector weirs closure with hydraulic drive valve closure and necessary reconstruction of concrete pillars, bridgeheads and spans;
- fish ladder for agri-environment fish;
- superstructure of the engine room and footbridge
- reconstruction of the footbridge over the weir, weir control rooms, resolving dams, weirs bottom and coast protection;
- reconstruction of easy access road and yards, as well as energy infrastruction
- automatic and distant valves control system equipment, as well as facilities for monitoring system and construction safety.